The Background

  • The European Union (EU) has announced concrete plans to triple its data center capacity (currently estimated at 12 GW) within 5-7 years.
  • The EU’s AI Gigafactories tender, closing mid-November, targets up to seven facilities and over €30 billion in total investment, including €20 billion in private funding.
  • Entities from Pax Silica signatories, which include the UAE, are eligible to join many of these consortia, but face restrictions defined by upcoming EU legislation.
  • The UAE has announced concrete plans for data center investments of up to 6 GW in France, Italy and Germany, which remain at various levels of development.

The Regulation

At the center of Europe’s efforts to regulate data center investments is the Cloud and AI Development Act (CADA), tabled by the European Commission in June 2026. CADA matters for several reasons:

  • Accelerated buildout | Each EU Member State must designate acceleration zones with a 12-month maximum permit timeline. Through streamlined permitting and improved access to power, land and financing, CADA also seeks to reduce development bottlenecks.
  • Sovereignty requirement | CADA sets an EU-ownership bar for the most sensitive work. Sovereignty Level 3 and above require EU ownership and control. The only derogation is for countries with a GDPR-adequacy decision, which no GCC country holds. As it stands, Gulf-controlled cloud providers would be shut out of the highest-value public-sector workloads.
  • Foreign control rules | At Level 2, a non-EU-controlled provider must prove, through an annual audit, that no foreign government can access its data, switch off its service, or force it to apply foreign sanctions. This is an open question for operators running US-licensed AI chips. Banks, utilities and other critical-sector buyers may also adopt the same test when choosing providers.
  • EU added value | Public buyers must score bids on how much value they create in the EU, alongside price, making it more difficult for non-EU providers to win tenders.

The concrete details of CADA are currently under negotiation, and more changes may be forthcoming. The European Parliament aims to vote on the law in June/July 2027, which will be followed by negotiations with the EU Member States. In parallel, the EU has adopted a revised foreign investment screening regulation, applying from January 2028, and is preparing new energy and sustainability standards for data centers. Both will further influence the outlook for UAE investment in EU datacenters.

Data Center Plans In Ten Major EU Countries

Country Today Plan / outlook to 2030 Main projects
Germany

~3.0 GW

IT connected load, 2025 (Bitkom/Borderstep)

Government target

~6 GW by 2030

Microsoft Rhenish cluster, NRW — ~520 MW grid connection; part of €3.2bn programme; under construction

AM:PM, Rackwitz (Leipzig) — 500 MW; €4–6bn; early planning, no tenant yet

Telis (Carlyle), Mehrum — 500 MW; initial planning, build from 2028

Schwarz Digits, Lübbenau / Dummersdorf — 200 MW under construction (€11bn); 240 MW by 2033, up to 1 GW by 2045

France

714 MW

colocation and hyperscale, 2024 (EY / France Datacenter)

No MW target · forecast

~2.3 GW by 2030

Campus AI, Fouju — 1.4 GW (240 MW by end-2027, 700 MW by end-2029); MGX, Bpifrance, Mistral AI, Nvidia

SoftBank–Sesterce, Bosquel — 1 GW; site selected May 2026

Data4 (Brookfield), Escaudain — 700 MW; €5bn; preliminary works

Ireland

~2 GW

contracted demand; 23% of electricity use in 2025 (CSO)

No target · constrained

Growth dependent on power built out

Echelon, Arklow (Wicklow) — 200 MW campus; construction started

Art Data Centres, Ennis — 200 MW; €1.6bn; cleared by High Court March 2026, phase 1 by 2028

Herbata, Naas (Kildare) — €3bn, six buildings; permitted subject to grid connection

Netherlands

~0.6 GW

average load (5.1 TWh, 2024, CBS); Amsterdam 927 MW live colocation

No target · restrictive

Hyperscale campuses capped

Pure DC, Amsterdam — 78 MW; ~€1bn; leased to one hyperscaler, phased from 2028

Yondr, Amsterdam — 70 MW

Microsoft, Amsterdam + 4 hyperscales, Haarlemmermeer — permitted before 2022 rules; under construction

Italy

609 MW

installed IT load, 2025 (Politecnico di Milano)

No MW target · forecast

~1.4–2 GW by 2030

Khazna–Eni, Ferrera Erbognone — 500 MW; Khazna (G42/MGX) with Eni; in development

TechBau, Trino — 300–400 MW; €4bn; national strategic interest, first lot 2028

Apto, Lacchiarella (Milan) — 300 MVA; €3bn

QTS (Blackstone), Vimercate — ~220 MW; up to €2.3bn

Spain

439 MW

commercial IT capacity, end-2025 (SpainDC)

Forecast (industry)

~2.5 GW by 2030

QTS (Blackstone), Calatorao, Aragón — 300 MW; €7.5bn first phase

AWS, Aragón — multi-site; €15.7bn to 2033

Grupo VDR, Navarra — 300 MW; planned

Poland

~0.7 GW

2026 market estimate

No MW target · forecast

~1 GW by 2030

WBS Power, Baltic campus (Pomerania) — 3.2 GW in four phases; grid terms secured, permits pending

Microsoft — PLN 2.8bn cloud and AI expansion

Finland

~0.4 GW

live colocation (Knight Frank); national total not published

No target · grid data

~5 GW contracted

Pure DC, Seinäjoki — 550 MW+; €7.5bn; phase 1 (110 MW) financed and leased

Nebius, Lappeenranta / Mäntsälä — 310 MW (2027); 75 MW live + up to 70 MW (2027)

Google, four sites — ≥€13bn for 2027–28; Kajaani and Muhos paused for environmental review

Sweden

n/a

no national figure published

No target · grid data

~7.3 GW in grid queue

Brookfield, Strängnäs — 750 MW; up to SEK 95bn; 10–15 year build-out

EcoDataCenter, Borlänge — 250 MW, expandable to 600 MW; first building early 2027

atNorth, Långsele — 200 MW; completion 2027

Microsoft — $3.2bn expansion at Gävle, Sandviken and Staffanstorp

Portugal

<0.1 GW

Sines SIN01 31 MW; Lisbon ~25 MW IT (Colliers)

Government pipeline

>2.6 GW in 44 projects

Start Campus, Sines — 1.2 GW; SIN02 next; Nvidia GPUs for Microsoft via Nscale

Merlin Edged, Lisbon region — up to 1.3 GW planned; 80 MW under construction (Q4 2027)

AtlasEdge, Lisbon — expansion to 30 MW IT

Impact For UAE Investors

Current developments have a clear impact on UAE investors looking at EU data centers:

  1. As a Pax Silica signatory, the UAE has more access to the European data center market than most non-EU investors. This is an advantage that it can turn into opportunity.
  2. Announced bilateral deals provide additional leverage – currently UAE pledges include 3GW of capacity in France, 2GW in Italy and 1GW in Germany.
  3. According to the current CADA draft legislation, the most sensitive data center work in the EU will likely remain closed to UAE investors unless CADA is changed significantly.
  4. CADA’s sovereignty tests are applied to the provider not the owner of the infrastructure, which means that owning powered land and buildings providers an easier path for UAE investors.